On June 16th, after a total of 62 days from April 15th, the first Site Turnaround of BASF-YPC Company Limited was successfully completed.
Treated as a collection of simultaneous overhaul of all plants and utilities, execution of mandatory inspections and IPS II expansion work(e.g. the Tie-In points), the turnaround had been carried out towards a common goal of not only a successful Turnaround execution but also an operation with excellent safety performance. And the target has been achieved perfectly. Besides, it will provide strong support and guarantee to the IPSII expansion project.
- Investments in a state-of-the-art olefin platform to facilitate sustainable growth- New steam cracker complex will be backwards integrated into
On the afternoon of June 19, BYC held a Community Dialogue to deepen communication and cooperation with the neighboring communities and local governme
- Expansion to serve growing demand from various industries in the Chinese market- Newly built facilities to utilize renewable energy, aiming to signi
- The expanded and new plants startup by the end of 2023- Supporting the growing demand in the Chinese marketNanjing, China – April 28, 2022